McKinley and Broadwater:

Ahead of schedule. Will be saving money on storage.

Deferred Maintanence:

70 bond projects scheduled for this summer.

Middle Schools:

Footings have been put in for Heights Middle School.
In design phase in West End Middle School and putting out for bids next winter.
Heights Middle School budget: Under the original budget. They found 1.5 mil in efficiencies over last 4 months.
The are working on selecting a new general contractor for West End Middle School.

Middle School Study Group Update:

  • Looking at a change in the middle school concept. 
  • Where are we in the process? First meeting will be soon and SD2/BEA is working on an agenda. May 5th is the first meeting. LST/BEA/Teachers/Rob Rogers/Some Parents is composition of team. 
  • Want report done by early June. May entail some negotiations with BEA to approve. 
Budget Committee Application Process:
  • Moving discussion to regular board meeting
New Sodexo Contract:
  • Sodexo was only one to bid. 
  • Contract goes to 2020. 
  • Contract going to regular board meeting for approval.

No comments: