Ahead of schedule. Will be saving money on storage.
Deferred Maintanence:
70 bond projects scheduled for this summer.
Middle Schools:
Footings have been put in for Heights Middle School.
In design phase in West End Middle School and putting out for bids next winter.
Heights Middle School budget: Under the original budget. They found 1.5 mil in efficiencies over last 4 months.
The are working on selecting a new general contractor for West End Middle School.
Middle School Study Group Update:
- Looking at a change in the middle school concept.
- Where are we in the process? First meeting will be soon and SD2/BEA is working on an agenda. May 5th is the first meeting. LST/BEA/Teachers/Rob Rogers/Some Parents is composition of team.
- Want report done by early June. May entail some negotiations with BEA to approve.
Budget Committee Application Process:
- Moving discussion to regular board meeting
New Sodexo Contract:
- Sodexo was only one to bid.
- Contract goes to 2020.
- Contract going to regular board meeting for approval.